Full bathroom renovations, ensuites and second bathrooms. Licensed, insured and QBCC 15580495, working across Brisbane, the Gold Coast and Beaudesert.
Every bathroom renovation looks finished at the same moment, and you cannot tell from looking at a finished bathroom whether the part that matters was done properly. The tiling you can inspect. The membrane under it you cannot, and that is the bit that decides whether this bathroom is still fine in ten years or is quietly wetting the floor joists next door.
So that is what this page is mostly about. Not tapware.
In order, and with the waiting shown where it really falls.
Keeping the toilet, shower and basin in their existing positions is the biggest single saving available. Moving the toilet is the most expensive of the three because the drain has to reach the new spot at the right fall.
Relocating drainage under a timber floor is a different job to cutting a concrete slab. This one factor can change the plumbing cost substantially.
Rot in the frame, a previous membrane that failed, or a leak that has been feeding the wall for years. Nobody can see this before demolition, which is why we tell you the range in writing rather than pretending it cannot happen.
Large format tiles need a flatter substrate and more care. Patterns, mitred corners and full height tiling all add labour. The tile price per square metre is rarely the real cost difference.
A hobless or level entry shower looks better and is harder to waterproof, because the falls and the membrane have to do more work. Worth it, but it is not a free upgrade.
Routinely undersized in older Brisbane houses. A bathroom that cannot dry out grows mould regardless of how well it was waterproofed.
No prices on this page, on purpose. A bathroom quote given before the room is seen is a guess, and the guess is always missing the strip out. We would rather walk the room, tell you what we expect to find, and put it in writing.
Request a proposalA full bathroom is commonly a few weeks rather than a few days, and the waterproofing is the reason it cannot be compressed.
The membrane has to be applied in coats and each coat has to cure before the next one goes on, then the whole thing has to cure before tiling starts. That is dead time on site that cannot be shortened by adding people, and it is the step that gets quietly skipped on a job that is running late.
If someone quotes you a complete bathroom in under a week, ask them when the membrane cures.
In Queensland waterproofing a wet area is licensed work, and under the National Construction Code the waterproofing of wet areas must comply with AS 3740. You should receive documentation for it.
Keep that paperwork. It is what you will need if anything ever goes wrong, and it is what a buyer or a building inspector will ask for later.
One current detail worth knowing, because it changed and not everyone has caught up: QBCC guidance is that the membrane must be applied directly to the structural substrate, not on top of screeds or toppings.
Because it is the most expensive thing on the job to get wrong and the easiest thing to hide.
A failed membrane does not announce itself. It shows up a year or two later as a soft patch in the hallway, swollen skirting in the next room, or a stain on the ceiling below. By then fixing it means removing the tiles, the screed and the membrane and starting that part again, plus repairing whatever the water has reached.
It is perhaps 2 percent of the cost of a bathroom and close to 100 percent of the risk. We do not compress it and we do not let it be the thing that absorbs a delay somewhere else.
A bathroom replacement in the same location generally does not need building approval. Moving walls, changing the building envelope or altering structure does.
The plumbing is the part that is always regulated. It must be carried out by a licensed plumber and it is certified, no matter how minor it looks. And any building work valued over $3,300 including labour, materials and GST must be carried out by a QBCC licensed contractor.
Usually, but it is the most expensive fixture to move. A toilet needs a soil connection at the right fall, so moving it means getting a drain to the new position at the correct grade.
Under a timber floor that is often straightforward. In a slab it means cutting concrete, which brings in core drilling or saw cutting, possible engineering advice about cutting near structure, and making the slab good again.
Showers and basins are much more flexible. If the budget is tight, moving those and leaving the toilet where it is gets you most of the layout change for a fraction of the plumbing cost.
Common and very often worth it, particularly if you are adding bedrooms underneath an existing house. Adding a wet area where there was not one before means new drainage, new waterproofing, ventilation and usually building approval, so it is a bigger job than renovating an existing bathroom. It also tends to add more to how the house actually lives than a cosmetic refresh of the bathroom you already have.