Two percent of the cost. Nearly all of the risk.

Every bathroom renovation looks finished at the same moment, and you cannot tell from looking at a finished bathroom whether the part that matters was done properly. The tiling you can inspect. The membrane under it you cannot, and that is the bit that decides whether this bathroom is still fine in ten years or is quietly wetting the floor joists next door.

So that is what this page is mostly about. Not tapware.

What a bathroom actually involves.

In order, and with the waiting shown where it really falls.

  1. Strip out. Everything out back to the frame or the slab. This is when existing water damage turns up, and on bathrooms it turns up often. Our proposals say in writing what happens if it does.
  2. Repairs and framing. Any rotten timber replaced, framing adjusted for the new layout, niches and screen fixings framed before the sheeting goes on.
  3. Plumbing and electrical rough in. Licensed trades, set out to the new fixture positions, with the falls set for the drains. Exhaust ventilation planned here rather than added later.
  4. Wet area sheeting and screeding. The substrate the membrane will be applied to, set to the right falls toward the waste.
  5. Waterproofing. Applied in coats, directly to the structural substrate, with curing time between coats and before tiling. This step sets the length of the whole job and it does not get rushed.
  6. Tiling. Floor and walls, with the falls preserved so water goes to the waste rather than to the door.
  7. Fit off. Tapware, toilet, vanity, screen, mirror, towel rails, exhaust fan, lighting.
  8. Clean, documentation, walk through. You get the certification paperwork, not just a finished room.

Where bathroom budgets actually go.

No prices on this page, on purpose. A bathroom quote given before the room is seen is a guess, and the guess is always missing the strip out. We would rather walk the room, tell you what we expect to find, and put it in writing.

Request a proposal

Bathroom questions, answered properly.

How long does a bathroom renovation take?

A full bathroom is commonly a few weeks rather than a few days, and the waterproofing is the reason it cannot be compressed.

The membrane has to be applied in coats and each coat has to cure before the next one goes on, then the whole thing has to cure before tiling starts. That is dead time on site that cannot be shortened by adding people, and it is the step that gets quietly skipped on a job that is running late.

If someone quotes you a complete bathroom in under a week, ask them when the membrane cures.

Does bathroom waterproofing have to be certified?

In Queensland waterproofing a wet area is licensed work, and under the National Construction Code the waterproofing of wet areas must comply with AS 3740. You should receive documentation for it.

Keep that paperwork. It is what you will need if anything ever goes wrong, and it is what a buyer or a building inspector will ask for later.

One current detail worth knowing, because it changed and not everyone has caught up: QBCC guidance is that the membrane must be applied directly to the structural substrate, not on top of screeds or toppings.

Why is waterproofing such a big deal?

Because it is the most expensive thing on the job to get wrong and the easiest thing to hide.

A failed membrane does not announce itself. It shows up a year or two later as a soft patch in the hallway, swollen skirting in the next room, or a stain on the ceiling below. By then fixing it means removing the tiles, the screed and the membrane and starting that part again, plus repairing whatever the water has reached.

It is perhaps 2 percent of the cost of a bathroom and close to 100 percent of the risk. We do not compress it and we do not let it be the thing that absorbs a delay somewhere else.

Do I need council approval for a bathroom renovation?

A bathroom replacement in the same location generally does not need building approval. Moving walls, changing the building envelope or altering structure does.

The plumbing is the part that is always regulated. It must be carried out by a licensed plumber and it is certified, no matter how minor it looks. And any building work valued over $3,300 including labour, materials and GST must be carried out by a QBCC licensed contractor.

Can I move the toilet?

Usually, but it is the most expensive fixture to move. A toilet needs a soil connection at the right fall, so moving it means getting a drain to the new position at the correct grade.

Under a timber floor that is often straightforward. In a slab it means cutting concrete, which brings in core drilling or saw cutting, possible engineering advice about cutting near structure, and making the slab good again.

Showers and basins are much more flexible. If the budget is tight, moving those and leaving the toilet where it is gets you most of the layout change for a fraction of the plumbing cost.

What about a second bathroom or an ensuite?

Common and very often worth it, particularly if you are adding bedrooms underneath an existing house. Adding a wet area where there was not one before means new drainage, new waterproofing, ventilation and usually building approval, so it is a bigger job than renovating an existing bathroom. It also tends to add more to how the house actually lives than a cosmetic refresh of the bathroom you already have.

Bathroom needing doing? Send a photo and tell us whether you want the same layout or a new one. We will tell you which of the cost drivers above apply to your room before we quote it.

Request a proposal

Related

Kitchen renovations Home extensions See our work Everything we build
Call Request a proposal