From a like for like replacement to taking out a wall and starting again. Licensed, insured and QBCC 15580495, working across Brisbane, the Gold Coast and Beaudesert.
A kitchen is the renovation most likely to come back more expensive than quoted, and the reason is almost always the same. The cabinetry gets priced accurately and everything behind the cabinetry gets allowed for.
Plumbing moves, electrical upgrades, a wall that turns out to be load bearing, a floor that is not level, waterproofing where the old sink leaked for years. Those are the line items that turn a fixed price into a conversation about variations, and they are the ones we go looking for before we write a proposal.
New cabinetry, benchtops, splashback and appliances, with the sink and services staying roughly where they are. The quickest and by a clear margin the best value, because nothing structural and very little plumbing moves.
The kitchen gets rearranged within its existing walls. Now plumbing and power move, the floor may need work, and the sequence matters a lot more. Most of our kitchens are this one.
A wall comes out and the kitchen joins the living area. This is a structural job: engineer, beam, propping, building approval, and usually ceiling and floor work across both rooms to make the join look like it was always that way.
Kitchens go wrong through sequence more than through workmanship. This is the order we work in and why, so you can see where the waiting is built in and judge any other quote against it.
Why we show you this. Because a kitchen quote that does not account for two separate lead times in the middle of the job is not a timeline, it is a hope. If you are comparing us against someone else, ask them to put their sequence in writing.
Plan on being without a kitchen for a few weeks rather than a few days, and treat anyone promising a week with suspicion.
The part people underestimate is that cabinetry is made to measure after demolition, not before. Final measurements are taken once the old kitchen is out and the walls are square, then the cabinets are built. That lead time sits in the middle of the job and no amount of extra tradespeople on site shortens it.
What we do about it is sequence the job so the unavoidable wait happens while something useful is going on, and tell you up front which weeks you will be living on a microwave.
Usually yes, but the answer costs money if the wall is load bearing. A load bearing wall needs a structural engineer to specify a beam, temporary propping while it goes in, and building approval.
You cannot reliably tell from inside the room. We look at what runs above it, which way the floor joists and roof members span, and what is in the ceiling space. That is a site visit question, not an over the phone one.
A like for like kitchen replacement generally does not need building approval. Once you start moving structure, taking out a load bearing wall, or altering the building envelope, it does.
Separately, the plumbing and electrical work inside a kitchen renovation must be done by licensed trades regardless of how small the job is, and that work is certified. Any building work valued over $3,300 including labour, materials and GST has to be done by a QBCC licensed contractor, which a kitchen comfortably exceeds.
If the budget is tight, yes, and it is the single biggest saving available to you. Keeping the sink and the appliances roughly where the existing plumbing and power already are can take a meaningful amount out of the job without changing how the finished kitchen looks.
Moving the sink to the island is the decision that most often quietly doubles the services cost, particularly on a slab. Sometimes it is absolutely worth it. We would rather you make that call knowing the number than discover it in a variation.
Either of us, and we will tell you which is better for your job. Clients often get better appliance pricing than we do during sales, so there is no sense in us marking them up.
What we insist on is knowing the exact models before cabinetry is made, because cabinets are built around appliance dimensions. A substituted oven after the cabinets are built is a genuinely expensive mistake. Stone benchtops are templated after cabinets are installed, so they sit near the end of the sequence.
Planning a kitchen? Send us a photo of the room as it is now and tell us what annoys you about it. That is usually enough for us to tell you whether your idea is a simple job or a structural one.